Wednesday, December 15, 2010

The Road

The airport expansion project started its road construction 1st so that they can close the existing road to the terminal building lobby. From my observation the road is 50% done and hopefully by end of this month or early January.

When the road is almost completed, the existing road to the building will be close and the new road will be opened to public. 6 lanes compared to the existing 3 lanes. Much more convenient for those who only want to drop the passenger or waiting by the road side for the passenger instead of parking their cars at the new parking space.

There is a new building, Central Utility Building, still under under construction only reach to the footing level. That is the building that we need to expedite so that the existing utility building and the water tank beside the terminal building can be demolished for piling works after they moved in to the new Central Utility Building not far from the existing.

Sorry, I didn't have a photo to show to you today. I will upload it by tomorrow so that you can have a better and clearer view.

For the work sequences, expansion will be started on the left side and the right side before going to the center of the building which it will be the hardest part.